Lake Burton · Foundation
Wildcat Ridge
300 Wildcat Rd, Tiger
$2,300,000
Contract price
14% complete
The client's window

Jane and Rob Prescott last opened this build 5 days ago, from Nashville, TN.

Progress photos

6 days ago
Foundation
Posted by Dale WhitfieldJuly 10, 2026 · 9:30 AM

Footings are dug and inspected, and the first foundation wall forms are set on the lake side.

Footings inspected
Wall forms set
Site work
Posted by Chris ClayJune 27, 2026 · 10:15 AM

Driveway is roughed in and the building pad is cut. You can finally see the footprint against the ridge.

Building pad cut
Driveway roughed in

Decisions waiting on you

Whole house
Upcoming
Window package

Aluminum-clad wood with black exterior. Needs sign-off before the framing order goes in.

Selection $92,000

On the record

Foundation and waterproofingApproved
Rob Prescott · June 16, 2026

Draw schedule

View all
1
Permits and mobilization
$230,000
Funded
2
Foundation complete
$345,000
Submitted to the bank
3
Framing complete
$368,000
Upcoming
4
Dry-in complete
$322,000
Upcoming

Key dates

Foundation inspection
July 19, 2026
Inspection
Framing starts
July 30, 2026
Milestone