Draw schedule
Funded, submitted, and upcoming draws, with the key dates beside them, so a call becomes a glance.
Laurel Point
Funded to date $3,280,000 of $4,100,000
1
Permits and mobilization
Permits pulled, site mobilized
Funded
2
Foundation complete
Foundation poured and inspected
Funded
3
Framing complete
Framing and roof deck complete
Funded
4
Dry-in complete
Roof, windows, and exterior doors set
Funded
5
Mechanical rough-ins
Plumbing, electrical, and HVAC rough-in passed
Funded
6
Drywall and interior trim
Drywall hung and trim complete
Funded
7
Cabinets and finishes
Cabinets, counters, and flooring installed
8
Final and closeout
Final inspection and punch list complete
Key dates
- Final inspectionAugust 25, 2026
- Closing walkthroughSeptember 6, 2026
Cherokee Point
Funded to date $2,044,000 of $3,650,000
1
Permits and mobilization
Permits pulled, site mobilized
Funded
2
Foundation complete
Foundation poured and inspected
Funded
3
Framing complete
Framing and roof deck complete
Funded
4
Dry-in complete
Roof, windows, and exterior doors set
Funded
5
Mechanical rough-ins
Plumbing, electrical, and HVAC rough-in passed
6
Drywall and interior trim
Drywall hung and trim started
7
Cabinets and finishes
Cabinets, counters, and flooring installed
8
Final and closeout
Final inspection and punch list complete
Key dates
- InspectionRough-in inspectionJuly 18, 2026
- Cabinets deliveredAugust 6, 2026
- Move-in walkthroughDecember 13, 2026
Timpson Cove
Funded to date $713,000 of $2,850,000
1
Permits and mobilization
Permits pulled, site mobilized
Funded
2
Foundation complete
Foundation poured and inspected
Funded
3
Framing complete
Framing and roof deck complete
4
Dry-in complete
Roof, windows, and exterior doors set
5
Mechanical rough-ins
Plumbing, electrical, and HVAC rough-in passed
6
Finishes and closeout
Interior finishes and punch list complete
Key dates
- Framing completeJuly 22, 2026
- Framing inspectionJuly 25, 2026
- Windows deliveredAugust 9, 2026
Wildcat Ridge
Funded to date $230,000 of $2,300,000
1
Permits and mobilization
Permits pulled, site mobilized
Funded
2
Foundation complete
Foundation poured and inspected
3
Framing complete
Framing and roof deck complete
4
Dry-in complete
Roof, windows, and exterior doors set
Key dates
- InspectionFoundation inspectionJuly 19, 2026
- Framing startsJuly 30, 2026